Project Update from Bauberger AG

bauberger 12t

📢Project Update from our Member BAUBERGER AG

Bauberger has no limits.

They lifted a 12 tonned machine on to a building. With their heavy-duty moving skates they csn easily delivered the machine remote controlled with millimeter precision.

Details:
Right next to the airport in Birrfeld (AG), Bauberger Team moved a 12t machine at SUHNER Schweiz AG to a new building and unloaded and brought a second one into the production hall.
 
The existing machine had to be lifted from plant 2 through the roof hatch, positioned on their truck and moved to the main plant. At the new location, they moved the 12t machine directly from the bridge of the truck via the lifting platform onto the ramp and through the entrance gate into the new production halls. Thanks to their electric heavy-duty moving skates, they were able to move the machine remote controlled and with millimeter precision through the entrance gate to the new location. Finally, they positioned the machine on the machine feet in the trough and pre-levelled it.

🏗Special tools
·       Truck
·       Beams and steel plates
·       Forklift truck 5t
·       Electric 15t heavy-duty moving skates

👀Watch on YouTube:
https://lnkd.in/e7CYq93t

🔝Not even the sky can stop these guys.

#girn #baubergerag #project #logistics #global #industrial #relocation #factoryrelocationprojectplan #industrialplantrelocation #factoryrelocation #movingafactory #Industrialrelocation #plantrelocation #globalrelocators