Case Study from Bauberger AG

GIRN Bauberger A tram journey - with 66t of auxiliary material 1

BAUBERGER AG just had a challenging and heavy task to place a new underfloor lathe at a tram depot. At the end with a 60 tonnes of auxilary materials were required Bauberger executed the task perfectly safe and sound.


Details:

A tram depot is a complex and special building. There are countless rails and electrical overhead lines for the trams and many pits in between to enable maintenance work on the trams. And there is a basement under the entire building.


In order to place the new underfloor lathe with its weight of more than 16 tonnes into its new foundation, all these aspects had to be taken into account in detail during the planning phase. They required some special solutions.

In the end, more than 60 tonnes of auxiliary materials were required to unload the new machine from the delivery truck with two Montys, move it to the pit on special heavy-duty rail vehicles and to place it in its foundation.

Special equipment


4x lifting columns 15t incl. rails, beams

2x Montylift-16

1x forklift 5t

Truck loading crane

Truck-trailer combination

Special heavy duty rail vehicles